Hope Manor II Update #14

Hope Manor II Update #14

18-Jul-2014

   

Current Project Update #14:

Hope Manor II Apartments, Volunteers of America’s veterans housing facility is nearly complete.  We are finishing the painting and installing the flooring, carpeting and ceramic tile on all the floors.  We are also continuing to install the plumbing and electrical fixtures.  While on the outside of the building, we are installing the pavers, supplying the irrigation to the memorial park and cleaning the windows.