Current Project Update #11:

We are progressing nicely on Porta Coeli, Catholic Charities Housing Development Corp’s latest senior housing structure.  We’ve begun laying the masonry on the outside of the building.  While on the roof, we’re continuing work on the solar system for the hot water and have begun spreading the insulation.  Inside, we are continuing to install the plumbing supply lines and have begun the bath and shower installation.  Also, we are continuing to run the supply lines for the electric and have begun to pull wire throughout the building.